This case study covers a data centre installation in Denver, Colorado, delivered by Simplify Networks field engineers for one of our MSP partners. Over one week, working out of hours, our team built out three racks: installing servers, firewalls, switches and routers, and running the inter-rack and cross-rack cabling that tied them into the rest of the facility.
Project at a glance
| Location | Denver, Colorado, USA |
|---|---|
| Engaged by | An MSP partner (white label, under the partner’s brand) |
| Scope | Three racks: servers, firewalls, switches and routers installed, cabled and powered up |
| Network kit | Cisco and Fortinet |
| Cabling | Inter-rack cabling, cable runs to other racks in the facility |
| Duration | One week on site |
| Working hours | Out of hours, to avoid disruption in a live facility |
| Handover | Photos, port records and a completion report to the partner |
The brief
Our partner had won a data centre build for its client in Denver and needed experienced hands on site to deliver it. The partner’s own engineers were not based in Colorado, and the timetable did not allow for flying a team in for a week. They needed a field service partner who could take the design, turn up with the right people and tools, and send back proof that the build matched the plan.
The scope covered three racks in a working data centre: receiving and checking the equipment, mounting servers and network devices, running the cabling between racks and out to other racks in the hall, and powering everything up ready for the partner’s network team to bring it into service.
What our engineers did on site
Rack and stack
Engineers unboxed and checked each device against the bill of materials, recorded serial numbers, fitted rails and mounted the equipment to the partner’s rack elevations. That included servers, Cisco switches and routers, and Fortinet firewalls. Our engineers regularly work on server hardware from HP, Dell and IBM, so mixed-vendor builds like this one are routine. See how we approach rack and stack.
Inter-rack and cross-rack cabling
Once the kit was mounted, the team ran and dressed the copper and fibre between the three racks, then ran cabling out to other racks in the facility so the new build could connect to existing infrastructure. Every cable was labelled at both ends to the partner’s convention and recorded against the port map. Our structured cabling page covers how we scope this kind of work.
Power-up and handover
With the racks cabled, engineers powered each device, checked status lights and console access, and confirmed the links were up. The partner’s network team then completed configuration remotely while our engineers stayed on site and on the call, so any patching or physical changes could be made there and then.
Working out of hours in a live data centre
The facility was live, so the work was scheduled out of hours to keep noise, foot traffic and risk to neighbouring equipment to a minimum. That meant planning each night’s tasks in advance: which devices would be mounted, which cable runs would be completed, and what had to be tested before the team left. It also meant agreeing access, escorts and deliveries with the facility ahead of each shift.
The most valuable part of a build like this is often the hour around power-up. Keeping our engineers on a live call with the partner’s network team meant configuration could be checked against the physical layout as it happened, and any mismatch between the design and the real ports could be put right that night rather than on a return visit.
The result
The three racks were installed, cabled, labelled and handed over within the week, ready for the partner to bring into service. The partner received photos of every rack front and rear, the completed port records and a completion report, all in its own format so it could pass them straight to its client.
Why MSPs use Simplify Networks for data centre work
- White label by default: engineers represent the partner, with no Simplify branding on site or in reports. Read more about white-label field services.
- One point of contact: jobs are coordinated from London, with a 24/7 service desk that responds in under 30 minutes, all year.
- Coverage: more than 2,000 field engineers across the UK and 285 cities worldwide. See the coverage map and our USA page.
- Dispatch options: 4-hour, next business day or scheduled. See dispatch and SLAs.
Related reading: data centre services, smart hands, data centre decommissioning and our other case studies.
Questions partners ask about this kind of project
How long does a three-rack data centre installation take?
It depends on the kit and the cabling, but a build of this size, with servers, firewalls, switches, routers and inter-rack cabling, typically runs to around a week on site. This one took a week, worked out of hours.
Can your engineers work to our design and labelling standard?
Yes. We work from the partner’s rack elevations, port maps and naming convention, and hand back photos and a completion report in the partner’s format.
Do you work directly with end clients?
No. We only work with MSPs, systems integrators and IT service companies. Our engineers represent the partner on site, under the partner’s brand.
Can you do the same in other US cities?
Yes. We cover data centres and offices across the USA. See our US field engineer coverage or email hello@simplifynetworks.co.uk with the site address.
Planning a data centre build?
Send us the site, the rack elevations and your dates. We will confirm engineers and send our partner rate card.